Project timeline planner
Lay out your renovation in the order the work and the inspections actually happen. Enter each task's working days and what it waits on; get the finish date, the critical path and a calendar you can export. It saves on this device.
1. Project
Template durations are placeholders, not estimates for your job. Replace them with your contractor's schedule and your suppliers' lead times.
Finish date
Wed, Feb 24, 2027 with buffer
- Work finishesTue, Feb 9, 2027
- Working days on the critical path73
- Buffer11 working days
- Calendar days, start to finish118
Critical path: 1. Measure, design and choose materials → 2. Get written quotes, sign the contract → 3. Permit application and approval → 5. Demolition → 6. Framing changes → 7. Plumbing rough-in → 10. Rough-in inspections (plumbing, electrical, mechanical) → 11. Framing inspection → 12. Insulation, where walls are open → 13. Insulation inspection, if your jurisdiction requires it → 14. Drywall: hang, tape and finish → 15. Prime and paint → 16. Flooring → 17. Install cabinets → 18. Countertop templating → 19. Countertop fabrication and install (use the fabricator’s lead time) → 20. Backsplash → 21. Plumbing and electrical trim-out, appliances → 22. Final inspection → 23. Punch list and final walk-through
Added with their finish dates. Open your project plan →
Your browser is blocking storage, so this timeline won't be saved when you leave. Download the CSV to keep a copy.
2. Tasks
“After steps” lists the step numbers a task waits for, like 2, 3. Use 0 days for a milestone such as a permit approval or delivery.
3. Schedule
| # | Task | Days | Start | Finish | Slack |
|---|---|---|---|---|---|
| 1 | Measure, design and choose materials | 10 | Fri, Oct 30, 2026 | Thu, Nov 12, 2026 | critical |
| 2 | Get written quotes, sign the contract | 10 | Fri, Nov 13, 2026 | Thu, Nov 26, 2026 | critical |
| 3 | Permit application and approval | 10 | Fri, Nov 27, 2026 | Thu, Dec 10, 2026 | critical |
| 4 | Order cabinets and other long-lead items (use the supplier’s lead time) | 25 | Fri, Nov 27, 2026 | Thu, Dec 31, 2026 | 7 days |
| 5 | Demolition | 3 | Fri, Dec 11, 2026 | Tue, Dec 15, 2026 | critical |
| 6 | Framing changes | 2 | Wed, Dec 16, 2026 | Thu, Dec 17, 2026 | critical |
| 7 | Plumbing rough-in | 2 | Fri, Dec 18, 2026 | Mon, Dec 21, 2026 | critical |
| 8 | Electrical rough-in | 2 | Fri, Dec 18, 2026 | Mon, Dec 21, 2026 | critical |
| 9 | Vent hood / mechanical rough-in | 1 | Fri, Dec 18, 2026 | Fri, Dec 18, 2026 | 1 day |
| 10 | Rough-in inspections (plumbing, electrical, mechanical) | 1 | Tue, Dec 22, 2026 | Tue, Dec 22, 2026 | critical |
| 11 | Framing inspection | 1 | Wed, Dec 23, 2026 | Wed, Dec 23, 2026 | critical |
| 12 | Insulation, where walls are open | 1 | Thu, Dec 24, 2026 | Thu, Dec 24, 2026 | critical |
| 13 | Insulation inspection, if your jurisdiction requires it | 1 | Fri, Dec 25, 2026 | Fri, Dec 25, 2026 | critical |
| 14 | Drywall: hang, tape and finish | 5 | Mon, Dec 28, 2026 | Fri, Jan 1, 2027 | critical |
| 15 | Prime and paint | 3 | Mon, Jan 4, 2027 | Wed, Jan 6, 2027 | critical |
| 16 | Flooring | 3 | Thu, Jan 7, 2027 | Mon, Jan 11, 2027 | critical |
| 17 | Install cabinets | 3 | Tue, Jan 12, 2027 | Thu, Jan 14, 2027 | critical |
| 18 | Countertop templating | 1 | Fri, Jan 15, 2027 | Fri, Jan 15, 2027 | critical |
| 19 | Countertop fabrication and install (use the fabricator’s lead time) | 10 | Mon, Jan 18, 2027 | Fri, Jan 29, 2027 | critical |
| 20 | Backsplash | 2 | Mon, Feb 1, 2027 | Tue, Feb 2, 2027 | critical |
| 21 | Plumbing and electrical trim-out, appliances | 2 | Wed, Feb 3, 2027 | Thu, Feb 4, 2027 | critical |
| 22 | Final inspection | 1 | Fri, Feb 5, 2027 | Fri, Feb 5, 2027 | critical |
| 23 | Punch list and final walk-through | 2 | Mon, Feb 8, 2027 | Tue, Feb 9, 2027 | critical |
The order of work, and why it matters
The sequence isn't a matter of taste: inspectors have to see work before it's covered. The 2024 International Residential Code (IRC) lists the required inspections in section R109.1:
- Foundation, after trenches are dug and forms and reinforcing are in place, before concrete is placed.
- Plumbing, mechanical, gas and electrical rough-in, before anything is covered or concealed and before the framing inspection.
- Frame and masonry, after framing and bracing are in place and the rough-ins are approved.
- Other inspections at the building official's discretion, such as fire-rated drywall before its joints are taped.
- Final, after the permitted work is complete.
Section R109.4 adds that work that fails inspection can't be covered until the building official approves it. Cities add their own steps. Seattle, for example, inspects insulation after it's installed and before walls are covered. Montgomery County, Maryland, has inspectors do the framing, rough wiring and mechanical inspections together. Brainerd, Minnesota, and Twin Falls, Idaho, inspect drywall only in fire-rated assemblies. Ask your building department for its list and add those steps.
Wait times that belong in the schedule
- Concrete: Quikrete's data sheet for its Concrete Mix (No. 1101) calls for curing 5 days at 70°F or above, or 7 days between 50 and 70°F.
- Paint: Sherwin-Williams' Duration Home interior flat lists a 4-hour recoat time at 77°F and 50% humidity, longer when it's cool or damp.
- Flooring acclimation: Pergo's 2018 guide for Outlast+ laminate asks for at least 48 hours in the room, or 96 hours in very dry or humid climates. Other floors and brands differ: check the product's own instructions.
- Lead times: cabinets, countertops, windows and special-order fixtures. Get the date from the supplier and enter it as its own task.
Put dates in the contract
The FTC advises making sure a home improvement contract includes an estimated start and completion date. Some states require it: California's contractor law requires an approximate start and completion date, and a change order must say how it affects the completion date. Compare quotes and contracts with the contractor hiring checklist, keep the budget in the project planner or the budget spreadsheet, and work through the renovation checklist.
Common questions
What order should a remodel go in?
Design and permits first, then demolition, framing changes and the “rough-in” of plumbing, electrical and HVAC. Under the 2024 International Residential Code, the rough-ins are inspected before the framing inspection, and work can’t be covered until it’s approved. Then come insulation (some places inspect it), drywall, paint and finishes, then fixtures, the final inspection and your walk-through. Your local building department sets the exact list.
How long does a kitchen or bathroom remodel take?
It depends on the job, your contractor’s crew and the lead times for cabinets, countertops and fixtures, so we don’t give a number. The durations in our templates are placeholders. Ask each contractor for their schedule; the FTC says a contract should include an estimated start and completion date. Enter their numbers here to see the finish date and which tasks hold everything up.
What is the critical path?
The longest chain of tasks that depend on each other. A delay to any task on it delays the whole project; tasks off it have “slack” and can slip that many working days without moving the finish date.
Why add a buffer?
Inspections get rescheduled, deliveries slip and walls hide surprises. A buffer of extra working days at the end gives you a realistic move-in date to plan around, separate from the contractor’s schedule.
Where is my timeline saved?
In your own browser, on this device. Nothing is sent to us. Download the CSV or calendar file to keep a copy.
Sources
- International Code Council, 2024 International Residential Code, Chapter 1, R109 Inspections
- Seattle Department of Construction & Inspections, Residential inspection quick sheets
- Montgomery County, MD, Residential alterations building inspections (PDF)
- City of Brainerd, MN, Residential inspection procedures (PDF)
- City of Twin Falls, ID, Inspection scheduling for residential projects (PDF)
- Quikrete, Concrete Mix No. 1101 data sheet (PDF)
- Sherwin-Williams, Duration Home Interior Latex Flat (A95) product data sheet
- Pergo, Outlast+ installation guide, 2018 (PDF hosted by Home Depot)
- FTC Consumer Advice, How to avoid a home improvement scam
- California Business and Professions Code §7159
Formulas and figures last checked against these sources on. Spotted an error? Tell us and we'll fix it.